Talks continue over GMWDA contract

Infrastructure specialist Costain has said negotiations are continuing towards a settlement of the problematic PFI contract with the Greater Manchester Waste Disposal Authority (GMWDA).

The authority announced in this May that it intended to terminate its £3bn, 25-year, PFI waste processing deal with the Viridor Laing joint venture, for which Costain is acting as subcontractor.

In a trading update ahead of half-year results, the firm said discussions with the GMWDA and Viridor Laing were continuing.

The contractor added that a further announcement would be made ”as appropriate”.

As part of the deal, Costain won a £397m subcontract to design, construct and commission 46 waste facilities across Greater Manchester.

But the works have been beset with problems and Costain incurred losses of £15.1m in its H1 2017 results.

  • A version of this article first appeared on the website of our sister title Construction News.

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Links may be included in your comments but HTML is not permitted.